We build tilt wall offices, flex buildings and warehouses in Irving and Las Colinas, with crane height and airport review handled before lift day.

Crane height is the first question on any Irving tilt-up job, because part of Dallas/Fort Worth International Airport, including part of the Las Colinas area, lies inside the city. A mobile crane reaching 100 feet or more is a temporary tall structure, and near an airport it can trigger aviation review long before it matters to anyone else. We build tilt wall offices, flex buildings, warehouses and corporate support space in Irving, and we put the crane question on the first page of the schedule.

The reason to build here is access. SH 183, the Airport Freeway, runs east to west through the center of Irving. I-635, the LBJ Freeway, crosses the northern edge, and SH 114 and the President George Bush Turnpike form an X through the city. A tenant with product or people coming from several directions can get to an Irving address without crossing downtown, which is why owners keep asking for space here.

What we deliver is the shell, floor and site: a floor slab that doubles as a casting bed, panels with the finishes the tenant wants, and a roof that closes the building.

Airspace, approvals and the lift plan

Our process for an airport-adjacent site has three early steps. First, we map the building and crane footprint against the airport's height limits and ask the design team to confirm the requirement with the authority. Second, we choose a crane and boom configuration that fits those limits, which can mean a different machine than we would use on an open site. Third, we write a lift plan that lists panel weights, pick order, rigging, brace locations and wind limits.

Because a plan like that takes time to approve, we do it while the building is still in design review. We also plan for a backup lift date. Any change to crane position or height forces a new review, and a backup date keeps the crew employed while the answer comes back.

Office, flex and corporate support buildings

The Las Colinas community in Irving is planned and mixed-use, covers more than 12,000 acres, and is centered near the intersection of SH 114 and the Bush Turnpike, with an entertainment district and many large corporate tenants. It also has DART Orange Line service, which runs through Irving and Las Colinas to the airport. In that setting the useful tilt-up product is the one that blends office and light industrial space: a front of glass and reveal panels, and a rear with dock doors and a clear-span warehouse.

That is the flex office and warehouse category, and we also build free-standing office buildings where the program is mostly people. Airport-related users sometimes need cross-dock truck terminals, where freight moves across the building without being stored.

Corporate headquarters and the buildings around them

Irving's headquarters list is long and varied: an engineering and construction firm, a consumer products maker, a metals company and an electric retailer are all listed, and a heavy equipment maker announced in June 2022 that it would move its headquarters to the city. The 2021 to 2022 city report lists a bank, an energy company, an insurer, a telecom carrier and a software company among the top employers. We name the profile to show what the demand looks like, and we do not claim any of those companies as clients.

What follows from that profile is a need for office space, training facilities, data and operations rooms, and warehouse space for parts and supplies. Our page for medical and office owners describes how we think about the shell, and logistics and 3PL operators shows the freight side.

Dense sites and shared roads

Irving's freeway grid is also its constraint. Roads are heavily used, parcels can be irregular because of interchanges and frontage roads, and utility corridors cut through lots. We start with a survey and a title review that shows easements, because an easement through the middle of the building pad is cheaper to find in week one than in week ten.

Casting space is limited on small lots. In that case we may cast panels in stages, lift the first group, then use the cleared slab for the next group. This adds a few days and cuts the footprint we need. We will say honestly when a lot is too small for the plan on the table, and what a smaller building or a phased slab would do.

The line items that change an Irving number

Crane choice is the unusual one here. A taller or longer-reach machine costs more per day, and a restricted height can mean more picks per panel or a different lift geometry. Next comes site work: dense areas bring shoring, utility relocation, and limited staging, all of which raise general conditions. Then panel finishes, since an office-quality face with reveals and sealers costs more per panel than a plain gray warehouse wall.

We separate those three lines in the estimate. If the budget has to come down, the owner can see whether to trim the finish, the building height or the schedule, instead of watching one lump sum change without explanation.

Booking the crane and the batch plant

A lift in a congested metro starts with a reservation. The crane, the rigging crew, the batch plant and the panel hardware supplier all have calendars, and the earlier we book, the more likely the dates line up. We confirm the delivery route from the plant, the permitted truck hours and the staging area for panels and joists, and we ask the city about any lane-closure permits.

After the lift, the roof package is the priority. Joists and deck go on right away to tie the braced walls together, and roofing follows as soon as the deck is inspected. See joist and roof deck framing for that sequence, and roof system coordination for how we manage the handoff to the roofer.

Check your Irving site with us

Send the address, the program and the date you need to be dried in. We will tell you how the airport and the freeway grid affect the crane, the haul and the pad. If the building will sit near the field itself, read about DFW Airport. For parcels a few miles west, see Grand Prairie.

Common Questions

Does an airport nearby stop us from using a crane?

Not necessarily. It can require review of the crane's height and location, and sometimes a different crane configuration. We raise the question early so the answer arrives before the lift is scheduled.

Can tilt-up look like a corporate office building?

Yes. With reveals, color, sealers, glass entries and canopies, a tilt-up shell reads as a polished office. The structure behind it is the same slab, panel and roof system as a warehouse, so the savings carry over.

What does flex space cost compared with a pure warehouse?

Flex costs more per square foot because the office portion carries more windows, finishes and mechanical systems. The shell cost is often similar. We price the two parts separately so you can see the difference.

How do you handle a small lot on a busy road?

With a staged casting plan, tight staging and traffic control. We also look at whether a smaller footprint or a second story is a better answer than squeezing a large building onto the lot.